|
EPA is working closely with the Town of Montville, Connecticut and the Connecticut Department of Environmental Protection (CTDEP) to supervise the removal of electrical transformers containing polychlorinated biphenyls (PCBs) from the Wisniewski Superfund Site on Route 163 in Montville. The trustees of the Site are undertaking the removal under EPA oversight and have approved to remove all eight transformers and two associated capacitors from the property to a licensed off-site disposal facility.
EPA investigations of the property in November 2007 and January 2008 concluded that some of the transformers contained oil contaminated with PCBs. Testing of the soils in the surrounding area of the transformers did not reveal any PCB contamination above CTDEP’s most stringent residential cleanup criteria. Temporary spill containment will be constructed prior to the removal as a protective measure.
The cleanup is expected to begin within the next several weeks and be finished by the end of the summer. As part of the removal, some additional testing of the transformers will be performed, followed by the removal of the equipment to an EPA-approved treatment and removal facility.
For More Details Refer this URL: http://yosemite.epa.gov
More than 3,000 American Electric Power customers in and immediately around Ironton were without power as of press time Saturday, thanks to an equipment failure that affected much of the city's eastern end.
"We had a transformer that unsuccessful," AEP spokesman Takeysha Cheney said. "Unfortunately the problem was more concerned than we originally thought."
Cheney said it may be as late as 6 p.m. Sunday before service is totally restored.
Electricity examine failed just after 11 a.m. Saturday, just as the heat and humidity began to kick into high gear.
Cheney said some portable units are being brought in to service nursing homes in the affected area.
For More Details Refer : http://www.irontontribune.com
Even $1.3 million toys sometimes want to be returned. That was the case this week with Nixa's latest transformer, a 70 MVA behemoth. Nixa city officials were told by Southwest Power Administration workers that plates inside the transformer had shifted during transportation, either on the boat or the truck, and they did not feel easy refreshing it.
SPA workers got the crane back out and overloaded the 68.5 ton transformer on the tractor trailer again and headed back to Houston enroute to Brazil, its country of origin. In the meantime, New Madrid, Missouri's 70 MVA transformer, which was shipped alongside Nixa's new unit, is now in place in Nixa.The city of a little more than 3,000 near the Illinois border will receive the repaired MVA sent back for repairs, SPA officials said.
Brian Denney, electric superintendent for the city of Nixa, said the new transformer is energizing at this very moment, with potential to carry its load early next week.
“This transformer improve is a project recognized in the 2004 system study because of the load growth on the electric system," Colvin said. "The mutual project is approximately $1.3 million, with approximately $900,000 of that coming from the city of Nixa. This transformer replaces a 1960s model 25 MVA that has surpassed its lifetime and is too small to carry Nixa's electric load."
For More Details Refer This URL: http://www.nixaxpress.com
Needhams Electronics' EMP-21 general device programmer supports over 6600 devices and employs both USB and parallel ports for communication with Windows-based software. Needhams' new automated one touch' system allows the users to blank-cheque, erase, program, verify or any combination of these functions with the touch of a button.
The low profile, lightweight design of the EMP-21 makes it ideal for any desktop or briefcase, proving helpful for programming devices in the field. Its economical cost lends well to a wide variety of budgets and with the absence of a fan or power switch, wear and tear is almost nonexistent.
Measuring only 262 x 162 x 31 mm with a 50 mm high power transformer, the programmer, parallel port, USB cable, transformer, and Family Modules, jointly weigh in at less than 2,2 kg.
The EMP-21 is static-protected on the ZIF Socket, Family Module socket, parallel and USB port, and power connector. The static protection on the parallel port besides protects it from the 12 volts of a serial port.
For More Details Please Refer This URL: http://dataweek.co.za
Let, we first started to think about this when UNC was initially planning its Renaissance Computing Center. RENCI was being designed as the first building on a new campus. RENCI was designed at that time with a 15 megawatt (MW) data center. Once you start thinking about waste heat as a resource, it will lead a long way from where you started. UNC is in the moist southeast, in which all building is heating and cooling year round. The heat loop sent out hot water and returned warm water to the basement. The cool loop sent out chilled water and returned cool water to the basement. A easy heat pump to bridge the two, removing heat from the chilling loop and returning it to the heating loop would, he calculated, save 40% of our summer air conditioning costs . As much as half of your data energy may be used up by the conversion from AC to DC, mainly if you have a UPS and batteries. The entire most successful recycling is based on energy. Aluminum leads the way since it is economical dirt converted into a usable metal by binding energy; aluminum recycling is recycling frozen energy. Once you start thinking of every energy store, of every heat gradient as an energy source, building problems look like opportunity. Zero net energy buildings may be summed up in the phrase local generation, storage, and conversion of energy. You can start on local change today.
The famous Hollywood Casino gone astray with no power for the short term last night subsequent to a transformer blew, as per the sources from the general manager Gary Luderitz. A disaster generator powered its way in following about 60 seconds, and in a large amount of cases the slit equipments were retained at that time, he revealed. Power was ousted in one segment for longer duration, requiring consumers to linger by their machineries for a couple of hours in order to acquire their payoffs, Luderitz revealed. Casino employees had to formulate labor-intensive payoffs, causing hindrances, he said. Firefighters from the Grantville Fire Company acted in response to the panorama as a preventative measure.
A fired-out transformer put off 11,000 homes into darkness in Belgrade and Rome on Saturday morning. Central Maine Power Co. had intended a shorter time devoid of power while employees de-activated a power transformer, but the transformer caught fire, as per the news revealed by the company spokeswoman Gail Rice. "It ought to have been about a 5 hour outage, and it crooked into a 12 hour outage," she reported. "It was a very huge transformer ... We don't don't usually stock those bulky ones, so we had to move quickly to find one." Rice revealed that the company programmed the swap-out for midnight on Friday in order to boast the new transformer in place prior to daylight Saturday.
|
|
Previous
Posts
Electrical Transformers to be removed from Montvil...
Thousands without power in Ironton
Leaving so soon? Faulty transformer heads back out...
Device programmer with USB and Parallel ports
Stop throwing – Energy Recycling
Casino goes dark-Courtesy blown transformer
Transformer failure shuts-down power at 11,000 hom...
MTL launches the new aura of transformers
5V MIL-STD-1553 Transformer designed with slighter...
Smithfield Foods Experiences power outage - Culpri...
Archives
November 2007
December 2007
January 2008
February 2008
March 2008
April 2008
May 2008
June 2008
July 2008
|